Construction is underway in Alberta on the twinning of the Trans Mountain pipeline to the B.C. coast. (Trans Mountain)

Landowner hearings begin for Trans Mountain expansion in Alberta

Detailed route talks start in Spruce Grove, in B.C. communities soon

The Canada Energy Regulator has begun its detailed route hearings on the Trans Mountain pipeline expansion project, starting with Alberta locations that are in dispute by property owners and moving to B.C. in the weeks to come.

The first two hearings were held Tuesday in Spruce Grove, with the first B.C. hearing in Kamloops in March and more to come along the expansion route through Merritt and into the Lower Mainland in the months ahead as more hearing orders are issued, a spokesperson for Canada Energy Regulator told Black Press.

“Detailed route hearings are required where an objection to the detailed route exists, and allow the commission to decide on whether the exact location of the pipeline is the best possible, and to confirm the most appropriate methods and timing of construction,” the regulator said in a statement released Tuesday.

RELATED: Industry cheers rejection of B.C.’s Trans Mountain suit

RELATED: Pipeline contractors hiring in tight skilled labour market

“Landowners whose lands are proposed to be crossed by the pipeline, as well as Indigenous groups and other persons whose land may be adversely affected were able to object to the detailed route proposed by Trans Mountain. The commission granted detailed route hearings where material changes in circumstances were identified since 2018, or where hearings had been granted but not completed prior to the court decision stopping the project in 2018.”

The twinning project runs for 1,147 km on a pipeline approximately 150 metres wide. It was re-approved by the federal government in June 2019, after additional consultation required by the Federal Court of Appeal.

Construction is underway along the Alberta portions, as well as the Edmonton and Burnaby terminals and the Westridge Marine Terminal. Trans Mountain Pipeline ULC, the company formed by the Justin Trudeau government to own and operate the 1954 pipeline and its expansion project, submitted its latest construction schedule to the regulator on Jan. 2.

From the Greater Edmonton section, the Trans Mountain right of way goes to Edson, Hinton, Spruce Grove, Stony Plain and Wabamun before reaching the Jasper-Mount Robson stretch where twinning was completed a decade ago. Entering B.C. in the North Thompson region, the pipeline route goes by Avola, Barriere, Blue River, Clearwater, Valemount and Vavenby, a region where the forest industry has been wound down due to market conditions and loss of lumber to beetle infestations and fires.

From there the Trans Mountain line goes past Kamloops and Merritt, then down the Coquihalla Pass to Hope, Chilliwack, Abbotsford, Langley, Surrey, Coquitlam and Burnaby.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

BC legislatureTransMountain

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

School demolition brings up memories

Darlene ‘Dar’ Hastings couldn’t wait to attend the new 100 Mile High when it opened in 1960.

Volunteering ‘best way to expand your bubble’

Val Severin serves the community as a way to give back

Old Timers Hockey league seeks players

The Old Timers Hockey Association is looking for players and increased community… Continue reading

Work begins on Clinton seniors’ living facility

Work has recently begun on a 20-bed seniors’ living facility in Clinton.

Unofficial holidays: Here’s what people are celebrating for the week of Sept. 27 to Oct. 3

World Farm Animals Day, Drink Beer Day and Virus Appreciation Day are all coming up this week

QUIZ: Do you know what’s on TV?

Fall is normally the time when new television shows are released

Canadian ski resorts wrestle with pandemic-vs.-profit dilemma as COVID-19 persists

Few are actually restricting the total number of skiers they allow on the hill

Victoria-area RCMP locate high-risk sex offender thanks to help of taxi cab driver

Scott Jones wanted on a Canada-wide warrant, ‘a risk to women and girls,’ police say

A (virtual) walk around the world by 88-year-old B.C. man

George Doi says it’s simple: ‘I like walking’

Is it time to start thinking about greener ways to package cannabis?

Packaging suppliers are still figuring eco-friendly and affordable packaging options that fit the mandates of Cannabis Regulations

Join Black Press Media and Do Some Good

Pay it Forward program supports local businesses in their community giving

End of CERB means uncertainty for some, new system for others

As of a week ago, the CERB had paid out $79.3 billion to 8.8 million people

Horgan, Wilkinson trade barbs over MSP premiums, health care at campaign stops

Horgan called a snap election for Oct. 24 earlier this week

Most Read