Trans Mountain pipeline expansion cost jumps 70% to $12.6 billion

The estimate of $7.4 billion was made in 2017 by the previous owner

The cost to build the Trans Mountain pipeline expansion has jumped by 70 per cent to $12.6 billion from a three-year-old estimate of $7.4 billion.

President and CEO Ian Anderson says the company owned by the federal government has spent $2.5 billion to date, including the impact of delays and additional regulatory processes, leaving an additional $8.4 billion needed to complete the project, plus $1.7 billion of financial carrying costs.

He says the project is now expected to be in service by December 2022.

The estimate of $7.4 billion was made in 2017 by the previous owner, Houston-based Kinder Morgan, Inc., which sold the expansion project and the existing pipeline to the federal government in 2018 for $4.5 billion.

Opponents have attacked the greenhouse gas emission and oil spill risks of the pipeline project but they’ve also charged it will be a money-loser with unproved markets in Asia that will fail financially and leave the public holding the bag.

ALSO READ: Opponents in B.C. to ramp up protests against Trans Mountain pipeline

Anderson says the company is recommending that Ottawa, as owner and lender, set aside a further $600 million reserve for cost impacts beyond the control of Trans Mountain.

Opponents of the pipeline expansion have vowed to do whatever it takes to stop the project despite losing a legal challenge before the Federal Court of Appeal earlier this week.

The four First Nations who lost the court challenge on Tuesday have 60 days to seek leave to appeal to the Supreme Court of Canada.

The expansion project would triple the capacity of the existing pipeline between Edmonton and a shipping terminal in Burnaby, B.C.

The Canadian Press

Like us on Facebook and follow us on Twitter.

Trans Mountain pipeline

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

CRD Chair Margo Wagner advises Cariboo to avoid self-isolating in recreational properties

This will help avoid potentially overtaxing local healthcare services

COVID-19 case confirmed at Subway restaurant in Cache Creek

Customers who visited the site from March 25 to 27 are asked to self-isolate

CRD reminds residents to prepare for spring freshet

As temperatures warm up residents are asked to proactively address flooding issues

Environment Canada puts out snowfall warning

Drive BC warns of compact snow

CRD passes borrowing bylaw due to uncertainty with COVID-19 pandemic

‘We are not in a position that we need to borrow anything right now’: CRD CFO

B.C. records five new COVID-19 deaths, ‘zero chance’ life will return to normal in April

Province continue to have a recovery rate of about 50 per cent

Two inmates at prison housing Robert Pickton test positive for COVID-19

Correctional Service of Canada did not release any details on the identities of the inmates

BC SPCA launches matching campaign to help vulnerable animals after big donations

Two BC SPCA donors have offered up to $65,000 in matching donations

Anti-tax group calls for MPs, senators to donate scheduled pay raises to charity

Bill C-30, adopted 15 years ago, mandates the salary and allowance increases each calendar year

Two arrested after man lies about COVID-19 illness to stay in Victoria Airbnb for free

Victoria Police found stolen goods inside the occupied unit

Liberals delay release of 75% wage subsidy details, costs: Morneau

Program will provide up to $847 per week for each worker

No laws in B.C. to force businesses to offer refunds, even during a pandemic

Black Press Media talks to Consumer Protection BC on how to navigate during COVID-19

Most Read