Energy Minister Bill Bennett

Site C dam construction to start next summer

Province to take less revenue from BC Hydro to minimize its debt, says $8 billion project is the cheapest available option to meet demand

The B.C. government has given the go-ahead for BC Hydro to start construction on a third dam on the Peace River, with a delay of six months to try to work out settlements with area aboriginal communities and landowners whose properties will be flooded or cut off.

Energy Minister Bill Bennett said Tuesday an update of the construction costs upheld the $7.9 billion estimate for the Site C dam that was developed in 2010, but the estimate has risen.

Delaying the project six months from its original start date adds inflation and interest costs, and calculating the effect of the provincial sales tax replacing the HST bringing the total to $8.34 billion, and the province is establishing a “project reserve” of $440 million to bring the total estimated cost to $8.77 billion.

The project reserve is in case of unforeseen events such as a rise interest rates during the eight-year construction period.

BC Hydro CEO Jessica McDonald said the six-month delay provides time to work out agreements with Treaty 8 First Nations who have declined settlement offers. The federal-provincial environmental review panel gave the go-ahead for the project in May, but noted its unavoidable impacts on aboriginal hunting, fishing and trapping rights that are assured by the 1899 treaty.

A group of Peace valley landowners has already started legal action against the project, having refused offers from BC Hydro to buy their land. Aboriginal groups in Alberta, downstream of the project, have also started court action against it.

NDP leader John Horgan called the decision “a $9 billion gamble” and repeated his call for a review by the B.C. Utilities Commission to see if the additional power is going to be needed by the time the dam is operating in 2025.

The BCUC will determine BC Hydro rates in the years ahead, and how much they will go up to pay for the most expensive public construction project in B.C. history. The government plans to mitigate BC Hydro rate impact by reducing the dividend the government takes from the power company’s operations each year.

Bennett said a review of alternative clean energy sources, including wind, solar and geothermal power, showed they can’t compete on price because they are intermittent sources that would require backup power.

 

Just Posted

Ministry announces highway road work planned for 100 Mile House this spring

Drivers can expect delays and at times single lane, alternating traffic

New report on 2017 wildfires calls for better coordination with First Nations

Tsilhqot’in National Government documents 2017 disaster and lists 33 calls to action

BC Bus North service extended to September

Transportation ministers have extended the service, which was set to expire at the end of May

Annual 100 Mile House Easter Egg Hunt a great success

Around 200 kids showed up to scavenge for chocolate

Woman dies after suffering ‘medical event’ while driving north of Lac la Hache

Initial report was that an older female had driven into the side of a hill, was not responsive

VIDEO: Large dust devil swirls through town in B.C.’s interior

Residents look on as column climbs about 90 feet into the air

RCMP arrest B.C. man following threatening Vaisakhi Facebook post

Post made reference to pressure cooker bomb at massive Surrey parade

Second dump site of Dungeness crab discovered in northern B.C.

DFO confident new site related to larger April 2 dump

Northern B.C. high school student reaches 100,000 followers on YouTube

Voice actor, animator, Jericho Fortune has more than 30-million views on his channel GTAGAMER222

University mourns student who died in B.C. canoeing accident

Andrew Milner, 19, was in his second year with the University of Calgary’s basketball program

B.C. woman pleads for people to stop stealing daffodils meant to honour cancer victims

Cynthia Bentley honours memory of those lost to cancer by planting 100 daffodils each year

Canfor temporarily shutting down lumber mills across B.C.

Low lumber prices and the high cost of fibre are the cause of curtailment, according to the company

Two in critical condition, several still in hospital after Langley deck collapse

Close relative Satwant Garcha makes daily trips to visit those injured at the wedding

Allegedly intoxicated man arrested after 3 paramedics attacked at Kamloops hospital

Paramedics had transported the man to Royal Inlands Hospital for medical treatment

Most Read