Shovels could be in the ground on Trans Mountain by September, CEO says

Ian Anderson points to weeks likely required for NEB to reinstate 2016 regulatory record

The CEO of the Crown corporation building the Trans Mountain pipeline expansion says shovels could be in the ground by September following cabinet approval Tuesday of the long-delayed project.

Oil could be flowing in new segments of the pipeline between Edmonton and the West Coast by mid-2022, Ian Anderson said, about one year later than the timeline envisioned last August when the Federal Court of Appeal quashed its regulatory approval and halted all fieldwork.

“We’re excited, our shippers are excited and the communities we touch are excited along the pipeline corridor,” said the CEO of Trans Mountain Corp. during a conference call Wednesday.

“We’re confident now that our project will meet every standard, every regulation, every test and reflect the values and priorities and principles that we all care for as Canadians.”

The National Energy Board is being asked to reinstate the record from the previous regulatory proceeding in 2016 so that the project can be brought back to the same state of construction readiness as last summer, Anderson said, a process expected to take some weeks.

He said the fact the federal government owns the pipeline won’t change or hurry the process.

Two re-routing requests are still to be decided, he said, including one involving B.C.’s Coldwater reserve, although those processes aren’t expected to affect the timeline.

He said contractors are being mobilized, pipe is being stockpiled in yards in Alberta and B.C. and the Burnaby terminal on the West Coast is being made ready so that construction work can begin there as soon as permitted.

Anderson said there is no update on the last estimated project cost of $7.4 billion, while conceding that “time is money.”

Earlier Wednesday, Finance Minister Bill Morneau told a Calgary business audience the best way to convince a skeptical oilpatch that the expansion will actually be built is to go ahead and build it.

“What we said yesterday was that we renewed that (pipeline) approval,” Morneau told reporters.

“What’s happening today is we’re back at work. The re-permitting is happening starting today. We are going to get work going this construction season. I want people in Alberta and people across the country to know that intent is real.”

Last August, the Federal Court of Appeal ripped up the original federal approval of the 590,000-barrel-per-day expansion, citing incomplete Indigenous consultations and a faulty environmental review.

Dan Healing, The Canadian Press

Like us on Facebook and follow us on Twitter

Just Posted

Coach Isnardy: ‘This is the best we’ve played all season’

The Williams Lake Peewee Tier 3 Timberwolves skated to a silver medal during the weekend

Cemetery fees equalized for all South Cariboo residents

‘We came up with an average rate from all of the communities’

RCMP constables receive Award of Valour for actions during 2018 mudslides

They walked in four kilometres over several mudslides

Handcrafted items galore at the Winter Arts and Crafts Fair in 100 Mile House

Residents of the South Cariboo will have a chance to pick up… Continue reading

PHOTOS: NHL honours B.C. grandma’s battle against cancer in special match

Shea Theodore’s grandmother Kay Darlington dropped the puck at a special ‘Hockey Fights Cancer’ game

Mosaic Forest Management announces forestry shutdown

Thousands of forestry workers in Coastal B.C. will be affected by ‘curtailment’

Appeal dismissed for B.C. man who assaulted woman in ‘thoroughly modern’ fight over phone

‘Both were seeking evidence of cheating by the other,’ says B.C. Supreme Court in Nanaimo

Freezing rain on the way to B.C.’s Fraser Valley, Interior

Road conditions will be icy and slippery, Environment Canada warns

University of Victoria threatens any athletes who speak about rowing coach probe

Barney Williams has been accused of harassment and abuse

B.C.’s largest catholic archdiocese names 9 clergymen in sex abuse report; probes ongoing

Vancouver Archdioces presides over 443,000 parishoners in B.C.

Smudging in B.C. classroom did not affect Christian family’s faith, says school district lawyer

Lawyers make closing arguments in a Port Alberni case about the Indigenous cultural practice

Canadian Forces member charged with possessing magic mushrooms in Comox

Master Cpl. Joshua Alexander, with the 407 Maritime Patrol Squadron, facing two drug related charges

Most B.C. residents, including those hit by 2018 storms, not prepared for outages: report

Create an emergency kit, BC Hydro says, and report all outages or downed lines

Most Read