Ministry of Transportation moves forward with Highway 97 Interconnector for Quesnel

The plan for a highway bypass around Quesnel is in development for completion within five years

The Ministry of Transportation and Infrastructure (MOTI) is surging ahead with plans for the AR-1 North-South Interconnector.

At last night’s (Mar. 27) City Council Meeting, a Ministry delegation presented Phase II of the Quesnel Transportation Plan to City Council and around 20 people in the gallery.

The project is still in an early stage of infrastructure planning, said senior regional transportation planning engineer Kathryn Weicker.

“There are a number of steps that come after that,” she noted.

“We have been working on building a Highway 97 transportation plan [over the past few years], coming up with short-, medium- and long-term solutions.

“We are presenting an implementation plan to you today. As that plans come into play and projects come out of that plan, they will proceed through the subsequent stages – preliminary design, functional design and all the way to construction.”

Interconnector

The MOTI delegation recommended implementation of the North-South Interconnector, which would replace the Quesnel River Bridge and the railway bridge farther up river and travel around the North Quesnel neighbourhood out onto Two Mile Flat.

They explained that through the community engagement survey, which was available on their website from Feb. 7-21, they found that 84 per cent of respondents preferred the North-South Interconnector option. Just 16 per cent of respondents prefered the option to replace the two bridges and realign the highway via Legion Drive.

They also outlined how other options, including the North-South Industrial Connector (which would travel around Cariboo Pulp and cross the river to the North East of Two Mile Flat and travel north from there) and the East-West Connector (which proposed a route for vehicles travelling from the West to cross the Fraser River upstream and connect with Two Mile Flat) had been phased out in a previous stage of the study.

READ MORE: Majority of MOTI survey respondents in favour of North-South Interconnector

Despite having already been phased out, these options were mentioned in the survey and respondents were able to agree or disagree with the decision to remove these options from the evaluation process.

Fifty-seven per cent of resondents agreed that it was appropriate to phase out the North-South Industrial Connector, and again, 57 per cent agreed it was appropriate to phase out the East-West Connector.

“The statistics from that data shows us that we took a good approach and that the public is supportive of that approach,” said regional project manager Oliver Schwuchow.

The full Community Engagement Summary Report can be found at https://www.quesnelobserver.com/news/majority-of-moti-survey-respondents-in-favour-of-north-south-interconnector/.

Other recommendations

The MOTI delegation also recommended going ahead with the Racing Road and Quesnel-Hydraulic Road access management and the Front Street three-lane configuration, both with a timeline of up to five years.

Longer-term plans from the study recommend Two Mile Flat access management and further South Quesnel access management, with a timeline of 15 to 25 years.

READ MORE: Ministry of Transportation set for second bypass open house, Feb. 19

READ MORE: Mayor provides some clarifications on Quesnel bypass

Moving forward

While recommendations have been made, project managers must still seek funding from the Ministry in order to implement the project.

”For the North-South Interconnector, we will be putting in a funding reqeust to develop a business case and undertake further preliminary engineering to get a better handle on costing and scope,” said Schwuchow.

He said the Front Street project is moving forward this year.

“We are currently in the detailed design [stage] and we are trying to get a tender out this spring and construction complete by 2018.”

Plans for the Racing Road access management are also underway, with project managers having put in a request for the next level of design, he noted.

Feedback from council

Quesnel City councillors were invited to comment and ask questions of the delegation following their presentation.

Councillor John Brisco asked whether the homes that may need to be bought up to make way for the Interconnector would be bought at a fair market value.

“They will be paid fair market value, and that’s the assessed value of the home before the Interconnector is in place,” explained Schwuchow.

Coun. Ron Paull had a question regarding the timeline.

“At what point in that zero to five-year time window would the affected home owners be given the word, yes or no, [whether the project is going ahead] so they can get on with their lives?” he asked.

“Is it not unusual for the affected home owners, and the community generally, to have a big question mark hanging over them for two years? Maybe even three?”

Schwuchow said it is difficult to give concrete answers with regard to the timeline.

“Over the next year we will be looking at getting the funding for the business case development and preliminary design. If we are successful with getting that funding, over that next year we will build that case, and federal funding applications, and work on getting that certainty.

“When those go forward to the politicians provincially and federally, we will have a better answer of whether we have determined funding for the project,” he said.

He acknowledged it could take one or two years before the project has a definitive green light.

“It could take a year to two years to get an answer on this based on the funding and the proposals that go forward.

“Throughout the process we will be engaging back to the community to let them know where we are at with the project,” he assured.

Just Posted

Walk into the forest in the Showcase Gallery

Group exhibit is focussed on trees

More Than Wood Art Gallery in 100 Mile House shows off artists

‘There is so much talent. It’s amazing’

Chekhov’s gun

A weekly family column for the 100 Mile Free Press

What are you doing on your Christmas break?

Megan Balbirnie 103 Mile House “I’m probably staying home then we’re going… Continue reading

One of 100 Mile House’s greatest unsolved mysteries featured in The National

Two-part television documentary will air at 6 p.m. on Dec. 10 and 11.

WATCH: Visitors flock to Barkerville for Christmas event

Check out our video of all the fun at the historic site east of Quesnel

Boeser scores 3, Pettersson has 5 points as Canucks hammer Blues

Vancouver picks up impressive 6-1 win in St. Louis

B.C. police stop drunk driver who offered up burger instead of ID

Roadblock checks over the weekend found at least two other impaired drivers

In Canada, the term ‘nationalism’ doesn’t seem to have a bad rap. Here’s why

Data suggest that Canadians don’t see the concept of nationalism the way people do in the United States

Small quake recorded west of Vancouver Island

No injuries or tsunami warning after 5.4 rumble felt some 400 kilometres from Victoria

B.C. suspends Chinese portion of Asian forestry trade mission due to Huawei arrest

Huawei’s chief financial officer Meng Wanzhou was detained at the request of U.S. in Vancouver

Canadians spent $1.7 billion dollars online in December 2017

Online retail sales accounted for 3.4 per cent of total retail sales

2-year investigations nets $900,000 in refunds for payday loan customers

Consumer Protection BC says selling practices were ‘aggressive and deceptive’

China: Canada’s detention of Huawei exec ‘vile in nature’

Huawei is the biggest global supplier of network gear for phone and internet company

Most Read